A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?
- A.Ask the team member to learn the new system as on-the-job training.
- B.Issue a change request to extend the project schedule.
- C.Escalate the team member's performance to the project sponsor.
- D.Assign an experienced resource to support the team member.