A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. Th…

A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented. What should the project manager do?
  • A.Ask the team member to learn the new system as on-the-job training.
  • B.Issue a change request to extend the project schedule.
  • C.Escalate the team member's performance to the project sponsor.
  • D.Assign an experienced resource to support the team member.
Explanation
Option A: The project is at Risk of delay but has not been affected yet. Means there is still time for improvement. Cheapest and motivating team development method shall On Job training. Option D should be when dealing with impact of risk.

Reference: examtopics_top_comment