A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?
- A.Consult the risk register for an appropriate planned risk response and implement.
- B.Revise the project management plan and move the task to a time when the technical resource will be available.
- C.Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
- D.Update the lessons learned report and the risk log to reflect that this risk has materialized.