A project manager leads a software development project in a hybrid environment. During project planning, the project ma…

A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave. What should the project manager do next?
  • A.Consult the risk register for an appropriate planned risk response and implement.
  • B.Revise the project management plan and move the task to a time when the technical resource will be available.
  • C.Review the business requirement with stakeholders and exclude the task assigned to the technical resource.
  • D.Update the lessons learned report and the risk log to reflect that this risk has materialized.
Explanation
Selected Answer: A Hint is PM already identified this risk during Project Planning. Output of Identify Risk process is Risk register. Basically, a good PM w/ 4 values & 12 principles under PMI languages need to do this task with due diligent thus Risk register can be used later as sufficient reference regarding risk response plan when relevant risk happen. A is still the correct answer.

Reference: examtopics_top_comment