A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experi…

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project. What should the project manager do?
  • A.Reduce the number of approvers required to implement a change request
  • B.Request sponsor approval for all change requests to reduce the number of changes
  • C.Initiate the number of iterations to reduce the number of change requests
  • D.Add a fixed number of change requests allowed by the client on the project baseline
Explanation
An iterative approach makes sense, so understand the rationale, but "initiate the number of iterations" makes no sense. What does that mean? It's either bad sentence structure or just misleading on purpose.

Reference: examtopics_top_comment