A project team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed. The main issue is that the team member does not understand a new system that was recently implemented.
What should the project manager do?

## Correct Answer

_See scenario._

## Explanation

Option A:
The project is at Risk of delay but has not been affected yet. Means there is still time for improvement. Cheapest and motivating team development method shall On Job training. Option D should be when dealing with impact of risk.