You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activi…

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?
  • A.Expert Judgment
  • B.Decomposition
  • C.Rolling Wave Planning
  • D.Templates
Explanation
Templates are used to identify the typical schedule milestones in the Define Activity process. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining activities.

Reference: examtopics_answer_description