# PMI-SP — Question 605

**Type:** multiple_choice
**Topics:** topic_1

## Question

You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule milestones?

## Correct Answer

_See scenario._

## Explanation

Templates are used to identify the typical schedule milestones in the Define Activity process. The tools and techniques used in defining the activity process are as follows: Decomposition: It is used to further divide the project work package into a more smaller and convenient form called activities. Rolling Wave Planning: It is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of
WBS. Templates: It is an activity list or a part of the activity list taken from the previous project and used in a new project. Expert Judgement: The skilled members in a project team or other experts who develop project scope statements can help provide knowledge in defining activities.

**Reference:** examtopics_answer_description

---
Source: https://hiexam.net/q/pmi/PMI-SP/605  
Practice (tracked): https://hiexam.net/study/PMI-SP/practice