You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:
//IMG//
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity D is delayed by two days?
- A.One
- B.Five
- C.Four
- D.Zero