A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that…

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?
  • A.Reactionary risks
  • B.Chain risks
  • C.Secondary risks
  • D.In flux risks
Explanation
"A secondary risk is a risk that arises as the result of implementing a risk response. If the risk response was not taken, the secondary risk would not exist." https://www.pmlearningsolutions.com/blog/residual-risk-versus-secondary-risk-pmp-concept-32

Reference: examtopics_top_comment