# PgMP — Question 604

**Type:** multiple_choice
**Topics:** topic_1

## Question

A risk response in a project in your program has actually caused new risks. What term is assigned to the new risks that a risk response has created?

## Correct Answer

_See scenario._

## Explanation

"A secondary risk is a risk that arises as the result of implementing a risk response. If the risk response was not taken, the secondary risk would not exist."
https://www.pmlearningsolutions.com/blog/residual-risk-versus-secondary-risk-pmp-concept-32

**Reference:** examtopics_top_comment

---
Source: https://hiexam.net/q/pmi/PgMP/604  