You are configuring project metrics for dashboards in Azure DevOps. You need to configure a chart widget that measures…

You are configuring project metrics for dashboards in Azure DevOps. You need to configure a chart widget that measures the elapsed time to complete work items once they become active. Which of the following is the widget you should use?
  • A.Cumulative Flow Diagram
  • B.Burnup
  • C.Cycle time
  • D.Burndown
Explanation
Selected Answer: C C: Cycle time is the Correct Answer.