You are configuring project metrics for dashboards in Azure DevOps.
You need to configure a chart widget that measures the elapsed time to complete work items once they become active.
Which of the following is the widget you should use?

## Correct Answer

_See scenario._

## Explanation

Selected Answer: C
C: Cycle time is the Correct Answer.