Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
  • A.Identifying high priority process improvements for the next Sprint.
  • B.The order of items in the Product Backlog.
  • C.How the team collaborates.
  • D.Documenting acceptance criteria for items in the next Sprint.