Which product records any project outcomes perceived as negative by stakeholders?

Which product records any project outcomes perceived as negative by stakeholders?
  • A.Business Case
  • B.Project Plan
  • C.Communication Management Strategy
  • D.Project Product Description
Explanation
D. Project product description. It contains customer quality expectations and acceptance criteria. I understand that buisiness case needs to be updated if negative outcomes realized - but the description what is perceived as a negative outcome sounds more like product description.

Reference: examtopics_top_comment