You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You woul…

You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?
  • A.Analogous estimating
  • B.Organizational process assets
  • C.Parametric scope definition
  • D.Template driven
Explanation
There is no type named template driven as per PMBOK. A is the correct answer

Reference: examtopics_top_comment