Once the project's WBS has been created what process may happen next?

Once the project's WBS has been created what process may happen next?
  • A.Estimate activity resources
  • B.Define activities
  • C.Estimate activity durations
  • D.Sequence activities
Explanation
The define activities process is the process that may begin once the project's WBS has been completed and approved. It is possible, in some projects, to complete the WBS and the activity list at the same time. Incorrect Answers: A: Estimating activity resources is dependent on the activity list, so this choice is not valid. C: Estimate activity durations are dependent on the activity list, so this choice is not valid. D: Sequencing the activities cannot happen until the activity list has been created.