hiexam
pmi · PMI-RMP · Q604 · multiple_choice · topic_1

At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks ha…

At the completion of a small project, the risk manager performs a risk audit and finds that several identified risks had occurred, and the impact was significantly larger than expected. While the project remained on schedule, the project budget increased by 50%. The project met all risk response milestones and no additional, previously unidentified risks, occurred on the project. Based on this information, what risk management process improvement should the risk manager recommend for future similar projects?
  • A.Increase frequency of risk management meetings with the project manager.
  • B.Revise the level of accuracy of probability and impact scores.
  • C.Document the risk audit report and capture it in the lessons learned database.
  • D.Expand the use of risk identification techniques.
Explanation
Should be B

Reference: examtopics_top_comment

Practice with progress tracking

Sign in to track wrong answers, get spaced-repetition reminders, and run timed exam mode.