Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What…

Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles. What should the project team do?
  • A.Note the changes to the restructure and roles that affect team activities
  • B.Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
  • C.Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project
  • D.Obtain a copy of the redefined key roles to update the stakeholder analysis
Explanation
Individuals and interactions over processes and tools. It should be B.

Reference: examtopics_top_comment