Early in a project, stakeholder analysis is performed; however, an organizational restructure redefines key roles.
What should the project team do?
- A.Note the changes to the restructure and roles that affect team activities
- B.Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
- C.Email a copy of the project vision to those redefined for key roles and ask if they need to be involved in the project
- D.Obtain a copy of the redefined key roles to update the stakeholder analysis