A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identi…

A project it just beginning, and management creates a long list of potential stakeholders. Which statement about identifying and engaging stakeholders is correct?
  • A.The project manager should identify and deal with stakeholders only during the execution phase.
  • B.Stakeholder satisfaction should be identified immediately and managed as a project objective.
  • C.The project manager should focus on project objectives and deal with stakeholders as a secondary priority.
  • D.Stakeholder satisfaction is the most important goal, and project objectives should be considered a secondary priority.
Explanation
B-Stakeholder satisfaction

Reference: examtopics_top_comment