You are the project manager for GHY Project and are working to create a risk response for a negative risk. You and the…

You are the project manager for GHY Project and are working to create a risk response for a negative risk. You and the project team have identified the risk that the project may not complete on time, as required by the management, due to the creation of the user guide for the software you're creating. You have elected to hire an external writer in order to satisfy the requirements and to alleviate the risk event. What type of risk response have you elected to use in this instance?
  • A.Transference
  • B.Exploiting
  • C.Avoidance
  • D.Sharing
Explanation
Selected Answer: C Risk avoidance This technique usually involves developing an alternative strategy that is more likely to succeed, but is usually linked to a higher cost.

Reference: examtopics_top_comment