# 3V0-624 — Question 606

**Type:** multiple_response
**Topics:** topic_1

## Question

A solution architect has been tasked with designing a new environment for a company's growing needs, and has obtained this information:
✑ Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.
✑ In a true disaster, the business can withstand a day of data loss and half a day of downtime.
✑ The company is one year into a 5-year contact with the co-lo data center.
✑ The building that is currently occupied no longer has any floor space available, but the company has 3 empty racks of space. The co-lo can provide up to
11KVA of power per rack.
✑ There are current contains with Dell to provide servers and with Cisco to provide the network components
✑ The network team has standardized on an end-to-end 10Gb network.
Based on this information, what are two requirements for the new design? (Choose two.)

## Correct Answer

_See scenario._

## Explanation

Correct Answer:
BC

- Uptime is critical during regular business hours when 95% of the transactions occur. Application uptime must be 99.9% during those hours.
- In a true Disaster, the business can withstand a day of data loss 24H RPO (Recovery Point Objective) and half a day of downtime 12 H RTO (Recovery Time Objective).

**Reference:** examtopics_top_comment

---
Source: https://hiexam.net/q/vmware/3V0-624/606  