Consider the following statements related to the TOGAF ADM.
1. All ADM activities are carried out within an iterative cycle of continuous architecture definition and realization
2. The Requirements Management phase is a continuous phase
3. Output from an early phase must not be modified in a later phase
4. The lifecycle of outputs must be managed through a versioning policy
Which statements are correct?

## Correct Answer

_See scenario._

## Explanation

Selected Answer: A
Statement 3 is wrong. 
Reference: https://pubs.opengroup.org/togaf-standard/adm/chap01.html
Note that output is generated throughout the process, and that the output from an early phase may be modified in a later phase.