# PRINCE2-Practitioner — Question 986

**Type:** hot_area
**Topics:** risk_management, project_planning, threat_responses

## Question

HOTSPOT -
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all.
Column 1 contains a number of possible risk responses to the above risk. For each risk response, select from Column 2 the appropriate risk threat response type that it represents. Each selection from Column 2 can be used once, more than once or not at all.
Hot Area:
//IMG//

## Correct Answer

_See scenario._

**Reference:** examtopics_top_comment

---
Source: https://hiexam.net/q/prince2/PRINCE2-Practitioner/986  
Practice (tracked): https://hiexam.net/study/PRINCE2-Practitioner/practice