# PRINCE2-Practitioner — Question 985

**Type:** hot_area
**Topics:** configuration_management, project_control

## Question

HOTSPOT -
The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
There is a major concern over an apparent lack of control of project documentation.
For each concern listed in Column 1, select from Column 2 the configuration management task that could help address the problem. Each selection from Column
2 can be used once, more than once or not at all.
Hot Area:
//IMG//

## Correct Answer

_See scenario._

---
Source: https://hiexam.net/q/prince2/PRINCE2-Practitioner/985  
Practice (tracked): https://hiexam.net/study/PRINCE2-Practitioner/practice