# PMP — Question 1423

**Type:** hot_area
**Topics:** kanban_board, bottleneck_identification, project_management

## Question

HOTSPOT -
A project manager receives an update that the development flow is not going well. Some team members cannot start their work because the delivery is late.
Looking at the Kanban board and the work in progress (WIP) lines, the project manager observes a bottleneck.
Click the title of the queue in the Kanban board below that requires additional resources to relieve the bottleneck.
Hot Area:
//IMG//

## Correct Answer

_See scenario._

**Reference:** examtopics_top_comment

---
Source: https://hiexam.net/q/pmi/PMP/1423  
Practice (tracked): https://hiexam.net/study/PMP/practice