You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?

## Correct Answer

_See scenario._

## Explanation

Conformance to schedule is a required adherence for the project's schedule. In this instance, the project manager must not allow the schedule to slip more than five percent.
Incorrect Answers:
B: This is the description of the schedule performance index.
C: This is not a valid statement about the project performance.
D: This is the description of the cost performance index.