# PMI-ACP — Question 603

**Type:** multiple_choice
**Topics:** topic_1

## Question

During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories.
What should the scrum master do?

## Correct Answer

_See scenario._

## Explanation

A. Ask the lead developer to identify a solution, and then share the details with the team
 = same as B. 
B. Ask a technical manager or architect to determine a solution to the problem
 = same as A. 
C. Work with the product owner to add a spike to the next sprint to identify a solution
 = Seems to be the best answer. 
D. Create a collaborative team environment so that the team can explore a solution together
 = As described, TEAM already did not find solution. Does not work without C - team need a spike for investigation.

**Reference:** examtopics_top_comment

---