# 1z0-063 — Question 605

**Type:** multiple_response
**Topics:** topic_1

## Question

Which two statements describe the relationship between a window, a resource plan, and a job class?

## Correct Answer

_See scenario._

## Explanation

yes A E

Windows work with job classes to control resource allocation. Each window specifies the resource plan to activate when the window opens (becomes active), and each job class specifies a resource consumer group or specifies a database service, which can map to a consumer group. A job that runs within a window, therefore, has resources allocated to it according to the consumer group of its job class and the resource plan of the window.

**Reference:** examtopics_top_comment

---
Source: https://hiexam.net/q/oracle/1z0-063/605  
Practice (tracked): https://hiexam.net/study/1z0-063/practice