# CCSP — Question 428

**Type:** multiple_choice
**Topics:** topic_1

## Question

Which value refers to the amount of time it takes to recover operations in a BCDR situation to meet management's objectives?

## Correct Answer

_See scenario._

## Explanation

The recovery time objective (RTO) is a measure of the amount of time it would take to recover operations in the event of a disaster to the point where management's objectives are met for BCDR.

**Reference:** examtopics_answer_description

---
Source: https://hiexam.net/q/isc/CCSP/428  